Ok guys… I’m a loooong time reader and second time poster. I am trying to get my shop open but am pulling my hair out. I negotiated a great deal on the lease using a previous post here as a reference! :lol: THANK YOU GUYS! I am supposed to sign off on the final lease on Tuesday. The deal is that my oven / hood issue is getting the best of me. My lease deal even includes a Lincoln 1000 that has been installed electrically as well as the gas line. I have tried locating the previous tenant and have had no luck… I would love to know why he failed as well as some questions about the oven/hood situation. Here are the facts:
F1 - The schematics for the L1000 shows that the existing hood is actually 12 inches too narrow in depth. The Lincoln 1000 barely fits under hood not allowing the spare 6" overhang in front and back. I can’t believe the Fire Marshal would have let him operate with that hood being too small.
F2 - Even though the hood is a type II hood, It doesn’t have the nozzles extended down into the conveyors. BTW… The Fire Marshal handling my area is strict about the Fire Codes. They even made a local chain around the corner install and then modify the fire suppression system so that two nozzles are aimed into the front and back of the conveyor openings of their double stacked MM’s. Thats a total of eight nozzles aimed into the MM’s. It’s a spiderweb of pipe that even had to be secured to the oven itself with brackets. Ridiculous! But whatev!
F3 - My crust is the product of 3 years and close to a hundred trial and error attempts and has been perfected. That being said, it was formulated with a stone-hearth oven in mind. What I’m saying is that my 100 attempts were performed in a commercial stone hearth pizza oven.
F4 - My original post was about a Roto-Flex oven and have since nixxed that idea due to lack of $$$ right now. I was hoping to grow into my ideal oven situation rather than sacrifice the $$ out of pocket right out of the gate. That means I would have needed to calibrate the fingers on the L1000 to cook my crust as close to my standards as i could get from an impinger. Now, that doesn’t even seem to be a cost effective option being that the hood is too small.
I’m calling on the experts here in the PMQ forums to maybe answer some questions and provide guidance for this lost pizza soul of mine.
Q1 - Is it possible to modify the existing hood by adding a 6" brow on each side, or add a 12" brow to the front of the hood as to make it deep enough to encompass the oven as the schematics call for?
Q2 - There is no Question 2… LOL! It seems to me the hood will have to be replaced if modification isn’t allowed by Fire Marshal… BTW - How did you guys get the Fire Marshal to inspect the property prior to applying for the Certificate of Occupancy?
Q3 - Just WTH… right? uuuggghhh!
Thank you in advance for your responses.
Yours truly…
“The deal killer”
F1 - The schematics for the L1000 shows that the existing hood is actually 12 inches too narrow in depth. The Lincoln 1000 barely fits under hood not allowing the spare 6" overhang in front and back. I can’t believe the Fire Marshal would have let him operate with that hood being too small.
F2 - Even though the hood is a type II hood, It doesn’t have the nozzles extended down into the conveyors. BTW… The Fire Marshal handling my area is strict about the Fire Codes. They even made a local chain around the corner install and then modify the fire suppression system so that two nozzles are aimed into the front and back of the conveyor openings of their double stacked MM’s. Thats a total of eight nozzles aimed into the MM’s. It’s a spiderweb of pipe that even had to be secured to the oven itself with brackets. Ridiculous! But whatev!
F3 - My crust is the product of 3 years and close to a hundred trial and error attempts and has been perfected. That being said, it was formulated with a stone-hearth oven in mind. What I’m saying is that my 100 attempts were performed in a commercial stone hearth pizza oven.
F4 - My original post was about a Roto-Flex oven and have since nixxed that idea due to lack of $$$ right now. I was hoping to grow into my ideal oven situation rather than sacrifice the $$ out of pocket right out of the gate. That means I would have needed to calibrate the fingers on the L1000 to cook my crust as close to my standards as i could get from an impinger. Now, that doesn’t even seem to be a cost effective option being that the hood is too small.
I’m calling on the experts here in the PMQ forums to maybe answer some questions and provide guidance for this lost pizza soul of mine.
Q1 - Is it possible to modify the existing hood by adding a 6" brow on each side, or add a 12" brow to the front of the hood as to make it deep enough to encompass the oven as the schematics call for?
Q2 - There is no Question 2… LOL! It seems to me the hood will have to be replaced if modification isn’t allowed by Fire Marshal… BTW - How did you guys get the Fire Marshal to inspect the property prior to applying for the Certificate of Occupancy?
Q3 - Just WTH… right? uuuggghhh!
Thank you in advance for your responses.
Yours truly…
“The deal killer”